Schedueld deployment date is wrong

Hi,

I’ve been trying to set up a scheduled deployment for the first time but it is scheduling it for the wrong date. The scheduled date is consistently 1 day and 1 hour before I selected. I have attached 2 screenshots to confirm - in the first you can see I am setting the deployment date for 1st April 2015 at 9:30am, and on the second you can see it is scheduling the deployment for March 31st 2015 at 10:30am.

Thanks, Ed

Hi Ed,

Thanks for getting in touch! We are aware of a bug with Daylight savings but we think it might be a similar issue here. Before I add an issue to investigate this further could you answer the following questions.
What timezone is the machine that you are accessing the Octopus interface set to?
What timezone is the Octopus Server set to?

Thanks!
Vanessa

Hello,

Both the machine I am accessing the Octopus server and the Octopus server are on UTC.

However, it is to be working now – I just tried another scheduled deployment for tomorrow and it did get the right date and time.

I’m happy to answer any other questions you have if you want to investigate further.

Thanks, Ed

Hi Ed,

Do let me know if this occurs again, and we will see if we can track it down.

Vanessa